Is there a provision for deemed registration of a real estate project in case the Regulatory Authority does not respond to the application?

Section 5 of the Act provides that the Authority has to decide on the application within 30 days of its receipt. It further provides that in case the Authority fails to take a decision within the said period of 30 days the project shall be deemed to be registered.